I am having trouble with Force completing activity.
Here's the simple business process model:
A --> B --> C
Scenario 1:
1) Happy path - works fine.
Scenario 2:
1) Start a new process Instance
2) 'A' will be in READY state. Work on Activity A. Finish it normally.
3) Process moves to activity B and will be in READY state.
What I am trying to do/achieve here is that FORCE COMPLETE activity B and the process should move to activity C.
4) when I am force completing activity B, I am actually seeing both B, C activities in the queue. And this new activity B is just an orphan task.
My common sense is telling me that this may be a bug in WID, but I am just curious if anyone had come across this issue and the fix if there is any. Is there any option setting that I need to set to stop this behavior.